Mercedes-Benz G-class (W463) since 1999 of release
1. Introduction
2. Governing bodies and operation receptions
3. Current leaving and service
4. Engine
4.1. Check of kompressionny pressure, assessment of a condition of cylinders
4.2. Engine check by means of the vacuum gage
4.3. Replacement of a belt of a drive of auxiliary units and elements of the mechanism of its tension
4.4. Check of pressure of impellent oil
4.5. Calculation of a consumption of oil
4.6. Check and adjustment of base provision of camshafts
4.7. Verification of the base provision of a balancing shaft (only M112 engines and 628)
4.8. Check of a condition of a chain of a drive of GRM on the M628 engine
4.9. Check of correctness of installation of a corner of an advancing of ignition on petrol models
4.10. Removal and installation of the power unit
4.11. Removal and installation of support of a suspension bracket of the power unit
5. Systems of cooling, heating, ventilation and air conditioning
6. A power supply system and production of the fulfilled gases
7. Systems of electric equipment of the engine
8. Automatic transmission
9. Transmission line
10. Brake and auxiliary systems
11. Suspension bracket and steering
12. Body
13. Onboard electric equipment
14. Schemes of electric connections


 









4-7-proverka-bazovogo-polozheniya-balansirovochnogo-vala-tolko-dvigateli-m112-i-628.html

4.7. Verification of the base provision of a balancing shaft (only M112 engines and 628)

М112

Verification of the base provision of a balancing shaft of the M112 engine

1 — Grooves in camshafts
2 — the Blocking plate of the right camshaft
3 — the Opening in a back counterbalance

4 — the Back counterbalance
And — the Pin in a case
In — Risk on a forward counterbalance

 PERFORMANCE ORDER

  1. Remove transmission assembly (see. Head Automatic transmission).
  2. Remove a driving disk.
  3. Check the base provision of camshafts (see. Section Check and adjustment of base provision of camshafts).

On the models equipped with the air pump it is necessary to dismantle also right combined valve which sealing laying is subject to replacement without fail.

  1. Establish blocking plates (2) on the right and left heads of cylinders, having filled them in grooves (1) camshafts.
  2. At the correct installation of a balancing shaft the opening (3) in a back counterbalance (4) should be combined with a nest in an engine case, - fill in openings a pin with a dimeter of 8.40 ÷ 8.55 mm. Make sure also of combination risks (In) on a forward counterbalance with a pin (And) in a case, - risk and a pin are located approximately in 22 cm below an interfaced surface of a head and are looked through through a window in the left cover of a drive of GRM.
  3. At violation of base installation it is necessary to replace a balancing shaft.
  4. Operating as it should be the return to a dismantle order, establish into place all acting in film components.

М628

Verification of the base provision of a balancing shaft of the M628 engine (1 of 2)

1 — the Gear wheel of an inlet camshaft
2 — the Gear wheel of a final camshaft
3 — the Cover
3а — Nizhny a bolt

3b — the Top bolt
5 — the Spring
7 — the Asterisk of a balancing shaft
9 — Adjusting labels

Verification of the base provision of a balancing shaft of the M628 engine (2 of 2)

5 — the Spring
6 — Marking

7 — the Asterisk of a balancing shaft

 PERFORMANCE ORDER

  1. Remove covers of heads of cylinders (see illustrations of the Detail of installation of covers of heads of cylinders of the M682 engine (1 of 2) and the Detail of installation of covers of heads of cylinders of the M682 engine (2 of 2)).
  2. Remove an intermediate cooler (Intercooler) of system of a turbo-supercharging (see. Head of the Power supply system and production of the fulfilled gases).
  3. Turn out the bottom bolt (3а) covers (3), - for the purpose of ensuring access to a bolt turn a cranked shaft in the normal direction.
  4. Bring the piston of the first cylinder into situation VMT.
  5. Turn out the top bolt (3b) and uncover (3).
  6. Remove a centrifuge.
  7. Make sure that the natyazhitel (9) provides demanded effort of a tension of a gas-distributing chain.
  8. Establish on a case a cover (3) and fix it the top bolt (3b).
  9. Turn a cranked shaft on two complete revolutions in the normal direction, again having brought the piston of the first cylinder into situation VMT.
  10. Again uncover (3).
  11. Make sure of correctness of base installation of camshafts (see. Section Check and adjustment of base provision of camshafts).
  12. Check correctness of base installation of a balancing shaft, a spring (5) which should occupy the situation shown in a picture, and marking (6) on an asterisk (7) to be slightly displaced concerning situation «at 12 o'clock».
  13. Operating as it should be, the return to a dismantle order, establish acting in film components on the places.
  14. In summary make reading of the DTC codes and cleaning of memory of system of onboard self-diagnostics by means of the STAR DIAGNOSIS scanner (6511 1801 00) (see. Head of System of electric equipment of the engine).


«previous page
4.6. Check and adjustment of base provision of camshafts
following page»
4.8. Check of a condition of a chain of a drive of GRM on the M628 engine